Lisemco delivery to Cau Rao II Bridge project
Lisemco handed-over module steel structure including steel girder- support for Cau Rao II Bridge project, so the total of delivery weight and erection is over 630 tons on 18/2.
Steel girder of Cau Rao II Bridge at Lisemco
Cau Rao II bridge project crossing Lach Tray river connecting Pham Van Dong street with Nguyen Van Linh street constructed on 10/3/2010. Cau Rao II bridge is to reduce the traffic situation of Cau Rao I and improve the urban face with Hang Kenh intersection completed the planning of Ho Sen-cau Rao II Bridge urban area infrastructure
Structure of steel girder cleaned and painted
According to contract signed with MT HØJGAARD, Lisemco fabricated 1257 tons of steel structure, current quantity is over 1000 tons ensuring the strictly technical requirement and strict supervision from MT HØJGAARD. The company is pushing the fabrication schedule up to complete the remaining quantity and transfer and erect at site.
Structure of steel girder
Transfering product erected at site
Assembly of Steel girder
Erection of steel girder in the North of cau rao river